CORPOELEC

PDVSA

CVG


EL FURRIAL PLANT

CLIENT
Petróleos de Venezuela (PDVSA)
LOCATION
El Furrial, Estado Monagas
START OF PROJECT
July 2010
STATE OF COMPLETION
100%
UNITS
4 X Rolls Royce Trent 60
MW
232MW (ISO)
NEW JOBS CREATED

1.645

MAN
HOURS

1.436.656

BENEFITING FAMILIES

174.000


SCOPE OF PROJECT

VIDEO


Engineering, Procurement and Construction of the new power plant. Water tanks, demineralized water system, DCS, substation, elevating transformers, control system room, administrative offices, workshop with bridge Crane.


LAS MOROCHAS PLANT, UNIDAD LM13

CLIENT
Petróleos de Venezuela (PDVSA)
LOCATION
Lagunillas, Estado Zulia
START OF PROJECT
May 2010
STATE OF COMPLETION
100%
UNITS
1 X General Electric LM2500
MW
22MW (ISO)
NEW JOBS CREATED

600

MAN
HOURS

101.200

BENEFITING FAMILIES

16.500


SCOPE OF PROJECT


Engineering, Procurement and Construction of the new unit. Civil, mechanical and electrical construction. Control system, air system, fire control and prevention system. Connection to the existing Las Morochas Generator Complex.


MORICHAL PLANT

CLIENT
Petróleos de Venezuela (PDVSA)
LOCATION
Morichal, Estado Monagas.
START OF PROJECT
July 2010
STATE OF COMPLETION
100%
UNITS
2 x GE LM6000 + Chillers
MW
105MW (ISO)
NEW JOBS CREATED

1.100

MAN
HOURS

335.000

BENEFITING FAMILIES

78.750


SCOPE OF PROJECT


Engineering, Procurement and Construction of new power plant. Control system, chillers, civil, mechanical and electrical construction, gas treatment plant, gas filter among others.


BARINAS PLANT I

CLIENT
Petróleos de Venezuela (PDVSA)
LOCATION
Barinas, Estado Barinas
START OF PROJECT
April 2011
STATE OF COMPLETION
100%
UNITS
2 X Pratt & Whitney Twin Pack FT4
MW
100MW (ISO)
NEW JOBS CREATED

1.230

MAN
HOURS

199.406

BENEFITING FAMILIES

75.000


SCOPE OF PROJECT


Engineering, Procurement and Construction of the new power plant. Liquid fuel system, fuel loading station, fuel tanks, fuel centrifugal system, de-mineralized water system and plant, DCS, recuperation of the existing substation, transport and removal of 24 motor-generators, ground movement and expansion of the installations in 2.5 hectares, construction of new roadways, environmental sanitation and ground recuperation, administrative offices, work shops and storage facility among others.